Caribbean Press Releases - http://www.caribbeanpressreleases.com
Barbados Professional Engineers Express Grave Concern About Highway Expansion Project
http://www.caribbeanpressreleases.com/articles/2441/1/Barbados-Professional-Engineers-Express-Grave-Concern-About-Highway-Expansion-Project/Road-drainage-needs-to-be-examined.html
 SC Admin
 10/9/2007
 
Bridgetown, Barbados -- Oct. 8, 2007 -- The Barbados Association of Professional Engineers (BAPE) has already expressed concerns about the ABC Highway expansion project being undertaken by 3S Structural Solutions LLC.

Road drainage needs to be examined

Bridgetown, Barbados – Oct. 9, 2007 -- The Barbados Association of Professional Engineers (BAPE) has already expressed concerns about the ABC Highway expansion project being undertaken by 3S Structural Solutions LLC.

These concerns include:

• the contract was agreed without a competitive tender process;

• the flyover solution was agreed before a traffic study was done; and this study was then undertaken by the same firm whose flyover proposal had already been accepted;

• the approval process for a project requiring such a large investment of public funds should have included a rigorous technical and economic feasibility study.

In addition to the company’s financial position, the qualification of a contractor to undertake this project should also have included consideration of the qualifications and experience of the key personnel, the nature of the contractor’s past experience, and a review of the firm’s litigation history.

Having observed the work in progress, BAPE questions whether full consideration has been given to the following areas which could negatively impact public safety and maintenance costs.

1. The drainage design at the superelevated sections (i.e. banked corners) of the highway between Wildey and Warrens appears to violate major road drainage engineering design principles. At superelevated sections, the entire width of the highway slopes in one direction, and rainwater would similarly drain in the same one direction. The design being built includes elongated horizontal slots near the base of the concrete medians to allow water to drain from the northbound lanes to the southbound lanes and vice versa.

During a recent period of heavy rainfall, it was observed that the volume of water flowing as a sheet across the southbound section was very significant. The danger is that this water could lead to hydroplaning, a loss of traction between vehicle tires and the road, and the loss of control of the vehicle, resulting in serious accidents. One of the worst possible locations to lose control of a vehicle is in a corner. To reduce the risk of hydroplaning, technical standards used in highway design provide recommended limits on the volume of sheet flow. Other problems associated with inadequate drainage are a potential reduction in the durability of the pavement surface and an increase in the splatter of water, which also has the potential to lead to vehicle accidents.

 
• BAPE recommends that 3S be asked to provide information on the standards used in the design of this road drainage system, and to identify where in the world they have constructed a similar road drainage design, so that the consequential effects can be examined.

2. Another safety concern is the location of the concrete islands at the Belle intersection. The islands are built along the continuation of the highway curb line, which on a highway such as this, means that they could present a collision danger to road users. It would be advisable that these be set back a minimum of 2 feet.

 • BAPE recommends that 3S be asked to provide information on the standards used in the design of this intersection, and examples of similarly constructed intersections they have designed elsewhere so that the consequential effects can be examined.

3. Based on observations of the spacing between street lighting fixtures it appears that fullcutoff fixtures rather than the previous semi-cutoff fixtures will be used. Full-cutoff fixtures put light on the ground below the fixture only, and do not emit light above 90 degrees. There is therefore less “uplight” and light pollution from the fixture.

This is desirable, however to achieve uniform lighting either more fixtures must
be used or the height must be increased – both of which have cost and energy use implications. Additionally, the lighting pole bases appear to be unusually small, raising concerns over the design wind speeds employed. 


Designs need critical review before they start

• BAPE recommends that 3S be asked to provide information on the type of street lighting selected for the project and the analysis carried out to determine the impact of this choice on maintenance and operating costs. They should also be asked to provide details of the wind speed and loads used in the design of these lighting poles and their supports.

4. It was observed that the original 75mm and 100mm conduits for the street lighting were removed and replaced with 50 mm conduits. The larger conduits in the original design would have permitted some redundancy in the cabling installed and therefore improved reliability of the street lights, i.e. a failure on one cable would not result in all lights failing at the same time. BAPE is concerned that the smaller conduits may not permit this level of redundancy.

• 3S should be asked to provide information on the street lighting design and the mitigation measures in place to address this concern.

5. There appears to be limited access across the long stretches of Jersey barriers (concrete median) for Police and Emergency vehicles should the need arise.


• BAPE recommends that some provision be made to allow for access across these barriers in the event of emergencies, and recommends that 3S be asked to address this concern.

6. Understandably, significant effort is being made by the contractors to allow continued use of the highway while construction is in progress. We are however concerned about the lack of safety night lighting and markings, primarily at the round-a-bouts and major junctions.
 

• BAPE recommends that measures be put in place to remedy this situation.

It is important to bear in mind that the foregoing is based on concerns expressed by some of our members who pass the site from time to time, and does not constitute a full engineering review. These queries simply serve to underscore the primary concern BAPE has held from the inception of this project, namely the absence of a technical and economic feasibility study preceding the project.

Perhaps the time has arrived when designs for significant public projects be made easily accessible (e.g. via the Internet) for critical review prior to their construction. The environmental and social impact studies for these projects should be made similarly available.

BAPE is mindful of its obligation to highlight issues which it believes present a potential threat to public safety. The design of all projects, particularly large, public infrastructure projects, should be critically reviewed before construction starts. One likely outcome of the failure to ensure the project has been planned using sound technical and financial principles is an increase in cost beyond the planned budget, when deficiencies must be corrected, or additional work is forced to be added to the scope.

 
THE BARBADOS ASSOCIATION OF PROFESSIONAL ENGINEERS
Roger Blackman
President – BAPE
www.bape.org