Bridgetown, Barbados – Oct.
9, 2007 -- The Barbados Association of Professional Engineers (BAPE) has
already expressed concerns about the ABC
Highway expansion project being undertaken by 3S
Structural Solutions LLC.
These concerns include:
• the contract was agreed without a competitive tender process;
• the flyover solution was agreed before a traffic study was done; and this study was then undertaken by the same firm whose flyover proposal had already been accepted;
• the
approval process for a project requiring such a large investment of public
funds should
have included a rigorous technical and economic feasibility study.
In addition to the company’s financial position, the qualification of a contractor to undertake this project should also have included consideration of the qualifications and experience of the key personnel, the nature of the contractor’s past experience, and a review of the firm’s litigation history.
Having
observed the work in progress, BAPE questions whether full consideration has
been given to
the following areas which could negatively impact public safety and maintenance
costs.
1. The drainage design at the superelevated sections (i.e. banked corners) of the highway between Wildey and Warrens appears to violate major road drainage engineering design principles. At superelevated sections, the entire width of the highway slopes in one direction, and rainwater would similarly drain in the same one direction. The design being built includes elongated horizontal slots near the base of the concrete medians to allow water to drain from the northbound lanes to the southbound lanes and vice versa.
During a recent period of heavy rainfall, it was observed that the volume of water flowing as a sheet across the southbound section was very significant. The danger is that this water could lead to hydroplaning, a loss of traction between vehicle tires and the road, and the loss of control of the vehicle, resulting in serious accidents. One of the worst possible locations to lose control of a vehicle is in a corner. To reduce the risk of hydroplaning, technical standards used in highway design provide recommended limits on the volume of sheet flow. Other problems associated with inadequate drainage are a potential reduction in the durability of the pavement surface and an increase in the splatter of water, which also has the potential to lead to vehicle accidents.
• BAPE
recommends that 3S be asked to provide information on the standards used
in the design of this road drainage system, and to identify where in the world
they have constructed a similar road drainage design, so that the consequential
effects can be examined.
2. Another safety concern is the location of the concrete islands at the Belle intersection. The islands are built along the continuation of the highway curb line, which on a highway such as this, means that they could present a collision danger to road users. It would be advisable that these be set back a minimum of 2 feet.
• BAPE recommends that 3S be asked to provide information on the standards used in the design of this intersection, and examples of similarly constructed intersections they have designed elsewhere so that the consequential effects can be examined.
3. Based on observations of the spacing between street lighting fixtures it appears that fullcutoff fixtures rather than the previous semi-cutoff fixtures will be used. Full-cutoff fixtures put light on the ground below the fixture only, and do not emit light above 90 degrees. There is therefore less “uplight” and light pollution from the fixture.
This
is desirable, however to achieve uniform lighting either more fixtures must
be
used or the height must be increased – both of which have cost and energy use implications. Additionally,
the lighting pole bases appear to be unusually small, raising concerns over the
design wind speeds employed.
• BAPE
recommends that 3S be asked to provide information on the type of street lighting
selected for the project and the analysis carried out to determine the impact
of this choice on maintenance and operating costs. They should also be asked
to provide details of the wind speed and loads used in the design of these lighting
poles and their supports.
• 3S
should be asked to provide information on the street lighting design and the mitigation
measures in place to address this concern.
5.
There appears to be limited access across the long stretches of
• BAPE
recommends that some provision be made to allow for access across these barriers
in the event of emergencies, and recommends that 3S be asked to address
this concern.
6.
Understandably, significant effort is being made by the contractors to allow
continued use
of the highway while construction is in progress. We are however concerned
about the
lack of safety night lighting and markings, primarily at the round-a-bouts and
major junctions.
• BAPE
recommends that measures be put in place to remedy this situation.
It
is important to bear in mind that the foregoing is based on concerns expressed
by some of our members
who pass the site from time to time, and does not constitute a full engineering
review. These
queries simply serve to underscore the primary concern BAPE has held from the
inception of
this project, namely the absence of a technical and economic feasibility study
preceding the project.
Perhaps
the time has arrived when designs for significant public projects be made
easily accessible
(e.g. via the Internet) for critical review prior to their construction. The
environmental and
social impact studies for these projects should be made similarly available.
BAPE
is mindful of its obligation to highlight issues which it believes present a
potential threat to public
safety. The design of all projects, particularly large, public infrastructure
projects, should be
critically reviewed before construction starts. One likely outcome of the
failure to ensure the project
has been planned using sound technical and financial principles is an increase
in cost beyond
the planned budget, when deficiencies must be corrected, or additional work is
forced to be
added to the scope.
THE
Roger
Blackman
President
– BAPE
www.bape.org